Case Studies
Projects delivered across six sectors
Six project accounts from recent engagements. Each describes the challenge, the approach and the measurable outcomes.
Government
Network infrastructure for a federal ministry
Designed, supplied and installed the structured cabling, active equipment and data centre for a ministry with 1,400 workstations across three buildings in Baghdad.
Workstations connected
1,400
Buildings covered
3
Delivery timeline
14 weeks
The challenge
The existing network had no documentation, mixed cabling standards from three different installation periods and insufficient capacity for the ministry's planned digital services programme.
Our approach
Conducted a full site survey before any procurement. Produced a complete as-built documentation set for the existing infrastructure before designing the replacement. Phased the installation to keep operations running throughout.
Outcomes
- 1,400 workstation connections on a single structured cabling standard
- New data centre with 24-hour UPS and diesel backup
- Full as-built documentation delivered at project close
- Network management system with real-time monitoring

Banking
Cybersecurity programme for a private bank
Delivered a full cybersecurity assessment, remediation programme and SOC setup for a private bank with branches in Baghdad, Basra and Erbil.
Critical findings resolved
47
Branches covered
3 cities
SOC go-live
16 weeks
The challenge
The bank had no documented security policies, no monitoring capability and had experienced two incidents in the preceding 18 months. CBI examination had flagged the security posture as requiring remediation.
Our approach
Started with a penetration test and vulnerability assessment to establish a baseline. Produced a remediation roadmap prioritised by risk. Implemented the remediation in parallel with designing the SOC. Trained the bank's internal security team to operate it.
Outcomes
- Full penetration test and vulnerability assessment report
- Remediation of 47 critical and high-severity findings
- SOC operational with 24/7 monitoring capability
- ISO 27001 readiness assessment completed

Banking
DigiBankFlex deployment for a state-affiliated bank
Implemented DigiBankFlex as the core banking system for a state-affiliated bank, replacing a 15-year-old legacy system while keeping 280,000 active accounts in operation.
Accounts migrated
280,000
Staff trained
120
Processing time
0.8s avg
The challenge
The legacy system had no API layer, no documentation and used a proprietary database format. Data migration required custom extraction tools. The bank could not accept downtime during the transition.
Our approach
Built a parallel-run environment and ran both systems simultaneously for 60 days. Developed a custom data extraction and transformation pipeline for the migration. Trained 120 staff before cutover.
Outcomes
- 280,000 accounts migrated with zero data loss
- Core banking, mobile banking and teller systems live
- Transaction processing time reduced from 4.2s to 0.8s
- Full CBI reporting compliance from day one

Oil and Energy
IoT monitoring network for an oilfield services company
Deployed an IoT sensor network across 18 field sites to provide real-time equipment monitoring, predictive maintenance alerts and fuel consumption tracking.
Field sites connected
18
Unplanned downtime reduction
34%
Sensors deployed
240+
The challenge
Field sites had no reliable connectivity. Equipment failures were only discovered after they caused downtime. Fuel consumption was tracked manually with no cross-site visibility.
Our approach
Installed cellular and satellite hybrid connectivity at each site. Deployed industrial IoT sensors on critical equipment. Built a centralised dashboard aggregating data from all 18 sites with configurable alert thresholds.
Outcomes
- Real-time monitoring across 18 field sites
- Equipment failure prediction reduced unplanned downtime by 34%
- Fuel consumption visibility across the full fleet
- Maintenance scheduling based on actual equipment hours

Logistics
Fleet management system for a logistics operator
Implemented MoveFlex for a logistics company operating 340 vehicles across Iraq, providing real-time tracking, dispatch management and driver performance reporting.
Vehicles tracked
340
Confirmation time
12 min avg
Deployment period
8 weeks
The challenge
Fleet operators had no visibility into vehicle locations once they left the depot. Route deviations, delays and fuel theft were identified only after the fact. Customer queries about delivery status required manual investigation.
Our approach
Installed GPS tracking hardware across the fleet. Configured MoveFlex for the company's specific route network and delivery types. Integrated with the customer's existing invoicing system. Trained dispatchers and fleet managers.
Outcomes
- 340 vehicles tracked in real time
- Average delivery confirmation time reduced from 4 hours to 12 minutes
- Fuel consumption anomaly detection active from week one
- Customer self-service delivery tracking portal live

Telecom
FTTH deployment for a regional ISP
Designed and deployed a fibre-to-the-home network covering 12,000 homes in a Baghdad residential district for a regional internet service provider.
Homes passed
12,000
Delivery timeline
22 weeks
Civil cost reduction
38%
The challenge
The ISP needed to compete with incumbent operators but had limited civil infrastructure budget. The deployment needed to cover a dense urban area with narrow streets and complex building access.
Our approach
Used aerial fibre deployment where possible to reduce civil works cost. Designed a distribution point architecture that minimised the number of splitters required. Managed the deployment in phases to allow the ISP to generate revenue before the full network was complete.
Outcomes
- 12,000 homes passed in 22 weeks
- Aerial deployment reduced civil costs by 38% versus underground estimate
- First 2,000 subscribers connected before full network completion
- Full NOC integration with the ISP's existing network management system

Discuss a similar project
If your requirements are similar to any of the projects described here, we can scope a proposal within five working days.